Gymnasium
Backfilling the foundation wall is about 50% complete. The south end of the basement has dried out enough for work to begin on
installing sanitary rough in for the locker rooms and basement toliets. The existing locker rooms have been gutted and the
concrete slab has been removed to install the new sanitary lines. Most of the ramp out of the basement has been removed and the
last few sections of the foundation wall is being formed.
Auditorium & Balcony
The sheet rock ceiling has been completed and painted. Scaffolding was removed on June 27th and the concrete floor was saw cut
and removed for the balcony foundation installation.
West Office
The walls and hollow metal door frames have been painted. The ceiling grid was installed and the new light fixtures dropped into place.
Cafeteria
Demoliton of the existing north wall of the cafeteria has begun. The insulated duct has been installed. The block work for the
addition has been completed.
Click here for more information
Some roofing and metal cap flashing needs to be installed by the roofer and the sidelights to the classroom doors still
need to be glazed.
The removal of topsoil and trees have begun for the Wanamaker school parking lot.
For more information about construction projects affecting the district read the minutes from the latest Board of Education
meeting. The most recent construction updates are located under Item 4 Administrator Reports article 4.02 Construction Update.
The road construction updates are under article 4.06 Update on Road Construction.